Workers work throughout National Day holiday to speed up construction of Ninh Binh-Hai Phong expressway
Thứ Hai, 31/08/2026, 21:41
Zalo
During the five-day National Day holiday, thousands of workers continued to diligently work on the Ninh Binh-Hai Phong expressway construction sites in an attempt to speed up construction progress.
Workers work throughout National Day holiday to speed up construction of Ninh Binh-Hai Phong expressway.
Taking advantage of favourable weather, workers at construction sites are maintaining three-shift per day.
Workers are working at Khanh Hoa's flyover construction site.
Nguyen Quang Minh, Director of the Ninh Binh Provincial Investment and Construction Project Management Board No.1, said that contractors are currently deploying all construction sites with approximately 500 machines and equipment and nearly 1,000, technicians, workers to work throughout the holiday to shorten the project completion time.
However, the construction still met several difficulties related to unprecedented weather development, some high technical items need concurrent construction. We are striving to shorten the project construction time and complete it for operation in 2026.
The Ninh Binh - Hai Phong expressway construction project’s section passing through former Ninh Binh province has a total length of 25.3 km.
To date, 217 hectares of cleared land has been handed over to contractors for construction.
The expressway is designed to have four lanes with a speed limit of 120 km per hour. The total investment is over 6.86 trillion VND from the central and provincial budgets.
The total construction volume currently stands at around 45.6% of the contract value. Total combined disbursed capital reached over 4,63 trillion VND.
Investor, contractors are focusing all resources, shorten the time, and accelerate the progress and complete it for operation in 2026.